16 years after it busted, Springbank Dam saga nears conclusion (2024)

The long saga of London's broken Springbank Dam should be finished by year's end, almost two decades after it busted during testing.

Author of the article:

Jane Sims

Published May 21, 2024Last updated 10hours ago2 minute read

Join the conversation
16 years after it busted, Springbank Dam saga nears conclusion (1)

The long saga of London’s broken Springbank Dam should be finished by year’s end, almost two decades after it busted during testing.

A report going to city council’s planning committee this week says the partial removal of the structure will start in July and be completed by the end of 2024.

Article content

It’s been 16 years since the bolts in the newly overhauled dam broke during early testing, rendering the structure unusable and ending the plan to enhance the Thames River for recreational activities upstream.

Advertisem*nt 2

Story continues below

This advertisem*nt has not loaded yet, but your article continues below.

16 years after it busted, Springbank Dam saga nears conclusion (2)

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Ryan Pyette, Dale Carruthers, Jane Sims, Norman De Bono and others. Plus, the Noon News Roundup newsletter on weekdays and the LFP Weekender newsletter on weekends.
  • Unlimited online access to London Free Press and 15 news sites with one account.
  • London Free Press ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.
  • Support local journalism.

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Ryan Pyette, Dale Carruthers, Jane Sims, Norman De Bono and others. Plus, the Noon News Roundup newsletter on weekdays and the LFP Weekender newsletter on weekends.
  • Unlimited online access to London Free Press and 15 news sites with one account.
  • London Free Press ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.
  • Support local journalism.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.

Sign In or Create an Account

or

View more offers

Article content

A fierce and lengthy debate followed to decide whether to fix the structure or to allow the river to flow naturally. While civil lawsuits flew and city hall dithered, time allowed natural vegetation and species to thrive.

In 2019, city hall was told the cost of removing the entire structure would be close to $6 million. City council opted for a partial decommission at half the cost. That will see the removal of the dam’s multi-tonne gates sitting on the riverbed, along with the hydraulic equipment and the control room. Left behind will be a concrete skeleton.

The staff report asks politicians to endorse a contract with Stantec Consulting to oversee the work and the restoration of 175 metres along the south bank of the Thames River, specifically “the environmental management, resident inspection and the construction administration.”

16 years after it busted, Springbank Dam saga nears conclusion (3)

The consulting costs are estimated to be roughly $728,000, bringing the total of engineering services for the project to about $1 million.

That’s only part of the cost to finally make the dam just water under the bridge. Almost all the work for entire project will be covered by the $3.775-million legal settlement reached with the gate engineers, with an additional $1 million to be added to cover inflation in construction costs, the report states.

Advertisem*nt 3

Story continues below

This advertisem*nt has not loaded yet, but your article continues below.

Article content

Stantec has been working on the project since it was awarded the design contract in 2021 with the hope the work could be finished in 2022. But the design period was extended to secure permits from federal and provincial agencies, the report states.

Bank restoration began in March when 43 out of 128 trees had to be removed, including several large silver maples. They will be replaced with 74 native species of trees.

Part of the contract will go toward fish rescue at a cost of $40,000 and to the hiring of six ecologists and divers who will be assigned to search, rescue and document any freshwater mussels. If found, the mussels would be relocated downstream, in line with federal guidelines relating to the at-risk species.

jsims@postmedia.com

Recommended from Editorial

  1. City garbage truck crashes, spills diesel into Thames River
  2. Damaged in 2008, the end finally arrives for Springbank dam

Article content

Comments

You must be logged in to join the discussion or read more comments.

Create an AccountSign in

Join the Conversation

Postmedia is committed to maintaining a lively but civil forum for discussion. Please keep comments relevant and respectful. Comments may take up to an hour to appear on the site. You will receive an email if there is a reply to your comment, an update to a thread you follow or if a user you follow comments. Visit our Community Guidelines for more information.

Trending

  1. Pair charged after owner helps London police track stolen vehicle
  2. Sentencing looms for driver, 79, who struck Girl Guides troop, killed child
  3. 16 years after it busted, Springbank Dam saga nears conclusion
  4. Man, 49, charged after Hyde Park business break-in: London police
  5. Mother wants London police to release details on daughter's shooting death

Read Next

Latest National Stories

    This Week in Flyers

    16 years after it busted, Springbank Dam saga nears conclusion (2024)
    Top Articles
    Latest Posts
    Article information

    Author: Rev. Leonie Wyman

    Last Updated:

    Views: 6388

    Rating: 4.9 / 5 (59 voted)

    Reviews: 90% of readers found this page helpful

    Author information

    Name: Rev. Leonie Wyman

    Birthday: 1993-07-01

    Address: Suite 763 6272 Lang Bypass, New Xochitlport, VT 72704-3308

    Phone: +22014484519944

    Job: Banking Officer

    Hobby: Sailing, Gaming, Basketball, Calligraphy, Mycology, Astronomy, Juggling

    Introduction: My name is Rev. Leonie Wyman, I am a colorful, tasty, splendid, fair, witty, gorgeous, splendid person who loves writing and wants to share my knowledge and understanding with you.